For a part of a construction project (the details of which are shown in Table No. 2, time m), the implementation of the paragraphs of
For a part of a construction project (the details of which are shown in Table No. 2, time m), the implementation of the paragraphs of this part was evaluated after 12 days From the start of work on it, the following was found: Activities (2-1), (3-1) and (4-1) were fully completed and (4-2) were completed in 4 days in full, activity (2-1) was completed in 7 days Activity (5-3) has completed one-fifth of it, activity (6-2) is half done, activity (6-4) has completed a quarter of it, and the other activities It has not started yet. It is required to update the project schedule and specify the time of completion and the critical path before and after the update
Agt. 1-2 3 a(day) m(day) b(day) 5 7 1-3 7 1-4 2 3 2-4 7 8 10 2-6 8 11 3-5 4 5 7 4-6 7 8 10 4-7 7 9 5-7 8. 11 6-7 2 3
Step by Step Solution
3.44 Rating (160 Votes )
There are 3 Steps involved in it
Step: 1
Solution critical 0 pathy completion duration before updat...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started