Question
1 Approved Answer
For a project with negative net present value, NPV, its discounted payback is ________. A. determinate with a positive number B. indeterminate, i.e., it will
For a project with negative net present value, NPV, its discounted payback is ________.
- A. determinate with a positive number
- B. indeterminate, i.e., it will never pay back
- C. determinate with a negative number
- D. None of the above