Question
For a proposed bridge project, FDOT has estimated the capital investment, annual O&M cost, net annual benefit, and salvage value under three different scenarios (optimistic,
For a proposed bridge project, FDOT has estimated the capital investment, annual O&M cost, net annual benefit, and salvage value under three different scenarios (optimistic, most likely, and pessimistic). Assume the useful life of the bridge is 50 years and the interest rate is 4%, what is the estimated average B/C ratio of the proposed project?
Capital investment
Annual O&M costs
Salvage value
Annual benefit
Optimistic
$9,787,429
$854,960
$1,600,000
$2,033,528
Most Likely
$11,628,574
$927,203
$1,500,000
$1,838,236
Pessimistic
$14,638,050
$1,269,950
$1,400,000
$1,791,369
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started