Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

For a proposed bridge project, FDOT has estimated the capital investment, annual O&M cost, net annual benefit, and salvage value under three different scenarios (optimistic,

For a proposed bridge project, FDOT has estimated the capital investment, annual O&M cost, net annual benefit, and salvage value under three different scenarios (optimistic, most likely, and pessimistic). Assume the useful life of the bridge is 50 years and the interest rate is 4%, what is the estimated average B/C ratio of the proposed project?

Capital investment

Annual O&M costs

Salvage value

Annual benefit

Optimistic

$9,787,429

$854,960

$1,600,000

$2,033,528

Most Likely

$11,628,574

$927,203

$1,500,000

$1,838,236

Pessimistic

$14,638,050

$1,269,950

$1,400,000

$1,791,369

image text in transcribed
For a proposed bridge project, FDOT has estimated the capital investment, annual O\&M cost, net annual benefit, and salvage value under three different scenarios (optimistic, most likely, and pessimistic). Assume the useful life of the bridge is 50 years and the interest rate is 4%, what is the estimated average B/C ratio of the proposed project

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing Cases

Authors: Frank A. Buckless, Mark. S. Beasley, Steven M. Glover, Douglas F. Prawitt

1st Edition

978-0130800015

More Books

Students also viewed these Accounting questions

Question

List noteworthy changes that were implemented in DSM-5.

Answered: 1 week ago

Question

What are the pyshcological flaws of Abner in burning barn

Answered: 1 week ago