For an activity in a CPM analysis, the early finish time is 2 0 and the late finish time is 2 0 . Which of
For an activity in a CPM analysis, the early finish time is and the late finish time is Which of the following statements is true?
Multiple Choice
The duration of this task is zero.
The activity is on the critical path.
The activity's late start must happen before its early start.
The slack for this activity is