Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

For an activity in a CPM analysis the Early Start time is 1 5 and the Late Start time is 2 0 . Which of

For an activity in a CPM analysis the Early Start time is 15 and the Late Start time is 20. Which of the following statements is true?
Question 8 options:
a)
The activity is not on the critical path.
b)
The duration of this task is 20.
c)
The slack for this activity is 20.
d)
The activity's late start must happen before its early start.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these General Management questions