For each of the precedence network diagrams listed below, determine the following values for each activity: (1 point for each answer) 1. The earliest start
For each of the precedence network diagrams listed below, determine the following values for each activity: (1 point for each answer) 1. The earliest start time 2. Earliest finish time 3. Latest finish time 4. Latest start time 5. Activity slack time 6. Identify the critical activities 7. Determine the duration of the project
Completion in 55 days