For questions 2 and 3 Project duration: 6 months Project budget (BAC): $3000 Elapsed time: 2 months Actual Cost (at 2 months) $1200 but you
- For questions 2 and 3 Project duration: 6 months Project budget (BAC): $3000 Elapsed time: 2 months Actual Cost (at 2 months) $1200 but you have completed 25% of the work.
- Planned Value at 2 months:
- Earned Value at 2 months: