Question

1 Approved Answer

For the 8-hour day shift in a hospital emergency room, the number of nurses needed, by day, is as follows: All day-shift nurses work five

For the 8-hour day shift in a hospital emergency room, the number of nurses needed, by day, is as follows:

All day-shift nurses work five 8-hour shifts per week and are entitled to two consecutive days off per week. Management would like to know a) the minimum number of nurses needed to provide the above capacity each day. (b) What will be the actual capacity by day? (c) What days will each nurse work?

Tour 1 = Tuesday to Saturday. Tour 2 = Wednesday to Sunday. Tour 3 = Thursday to Monday. Tour 4 = Friday to Tuesday.Tour 5 = Saturday to Wednesday. Tour 6 = Sunday to Thursday. Tour 7 = Monday to Friday.

Recall the nurse-scheduling problem (with full-time nurses only) introduced in class. We now know that this staffing plan cannot be achieved with fewer than 8 nurses. However, nurses prefer to work tour 7 because the days off are Saturday and Sunday. Nurses also like tours 1 and 6 because one day off is a Saturday or Sunday, respectively. Reformulate the problem so that it uses exactly 8 nurses but the number of nurses assigned to tours 1, 6 and 7 is maximized while meeting minimum daily staffing needs. How did you reformulate the decision variables, objective function and constraints?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Analysis For Management

Authors: Barry Render, Ralph M. Stair, Michael E. Hanna

11th Edition

9780132997621, 132149117, 132997622, 978-0132149112

More Books

Students also viewed these General Management questions

Question

' Which areas are you most dependent on to get your work done?

Answered: 1 week ago