For the above, calculate the project float and indicate the critical path of the project. Finish no later than day 35 as a constraint. begin{tabular}{|c|c|c|}

image text in transcribed

For the above, calculate the project float and indicate the critical path of the project. Finish no later than day 35 as a constraint.

\begin{tabular}{|c|c|c|} \hline Activity & Predecessor & Duration(Days) \\ \hline A & & 3 \\ \hline B & A & 3 \\ \hline C & B & 3 \\ \hline D & A & 7 \\ \hline E & D & 7 \\ \hline F & C,E & 3 \\ \hline G & E & 11 \\ \hline H & F,G & 4 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hospitals What They Are And How They Work

Authors: Donald J. Griffin

4th Edition

0763791091, 9780763791094

More Books

Students also viewed these General Management questions