For the following Project: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Crash Cost Immediate Predecessor A 4 3 $2,000 $2,100 - B 2
For the following Project:
Activity | Normal Time (weeks) | Crash Time (weeks) | Normal Cost | Crash Cost | Immediate Predecessor |
A | 4 | 3 | $2,000 | $2,100 | - |
B | 2 | 1 | $2,200 | $2,800 | - |
C | 3 | 3 | $500 | $500 | - |
D | 8 | 6 | $2,300 | $2,600 | A |
E | 6 | 3 | $900 | $1,200 | B |
F | 3 | 2 | $3,000 | $4,200 | C |
G | 4 | 2 | $1,400 | $2,000 | E, F |
If the project is to be shortened by 1-week, which activity will be reduced and how much will the cost be increased?
A, $100 | ||
E, $100 | ||
A. $100; E.$100 | ||
F, $1200 |
Please highlight the answer
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started