For the following schedule, assume that for each Job, analysis must be done prior to production, and production completed prior to testing, and testing done

For the following schedule, assume that for each Job, analysis must be done prior to production, and production completed prior to testing, and testing done prior to installation. Apply the critical chain process assuming that testing is a bottleneck resource (and that the other resources required are not constrained). Use due date as a basis for priority. Apply the critical chain process to schedule, identifying buffers by type:

Use resource buffers between bottleneck resource usages

Use feeder buffers after predecessor at interfaces between slack activities and critical activities

Use project buffer

Job

Analysis

Production

Testing

Installation

Due date

A1

4 weeks

4 weeks

4 weeks

2 weeks

Week 15

A2

4 weeks

4 weeks

4 weeks

2 weeks

Week 10

A3

4 weeks

8 weeks

4 weeks

2 weeks

Week 20

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hospitality Financial Management

Authors: Agnes L DeFranco, Thomas W Lattin

1st Edition

0471692166, 9780471692164

More Books

Students also viewed these General Management questions

Question

If X has distribution function F(t) = 0, t Answered: 1 week ago

Answered: 1 week ago