Question
1 Approved Answer
For the following table of information, Draw the network diagram Determine the critical path(s) Identify Slack time Activity Duration (Days) Dependency A 3 Start B
For the following table of information,
- Draw the network diagram
- Determine the critical path(s)
- Identify Slack time
Activity | Duration (Days) | Dependency |
A | 3 | Start |
B | 3 | Start |
C | 5 | A,B |
D | 7 | Start |
E | 8 | Start |
F | 3 | D, E |
G | 1 | C,F |
H | 3 | G |
I | 9 | G |
J | 2 | H |