Question

1 Approved Answer

For the project with Earned Value ( EV ) = $ 3 6 0 , Actual Cost ( AC ) = $ 4 0 0

For the project with Earned Value (EV)= $360, Actual Cost (AC)= $400. The original project budget is $1,000. Assuming the remaining work will be impacted by the current cost performance and current schedule performance, what is the Estimate At Completion ($EAC) of the project?
Question 17 options:
a)
1100
b)
1111
c)
1040
d)
1000

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Great Boss Great Management

Authors: S. M. H. Gibson

1st Edition

9798842893430

More Books

Students also viewed these General Management questions

Question

Timeline for implementation report

Answered: 1 week ago

Question

a. What aspects of the situation are under your control?

Answered: 1 week ago