Four jobs must be scheduled through a three machine flow shop. Determine the sequence and makespan (Cmax) of the three-machine flow shop problem using THREE
Four jobs must be scheduled through a three machine flow shop. Determine the sequence and makespan (Cmax) of the three-machine flow shop problem using THREE of the following three heuristics. (Select all the algorithms, and do it separately) (1) Palmers Algorithm (2) CDS Algorithm (3) Critical Job Algorithm The processing time of each job on each machine is given in following table.
Job 1 | Job 2 | Job 3 | Job 4 | |
Machine 1 | 6 | 8 | 3 | 4 |
Machine 2 | 6 | 3 | 6 | 4 |
Machine 3 | 7 | 4 | 4 | 2 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started