Four jobs must be scheduled through a three machine flow shop. Determine the sequence and makespan (Cmax) of the three-machine flow shop problem using THREE

Four jobs must be scheduled through a three machine flow shop. Determine the sequence and makespan (Cmax) of the three-machine flow shop problem using THREE of the following three heuristics. (Select all the algorithms, and do it separately) (1) Palmers Algorithm (2) CDS Algorithm (3) Critical Job Algorithm The processing time of each job on each machine is given in following table.

Job 1 Job 2 Job 3 Job 4
Machine 1 6 8 3 4
Machine 2 6 3 6 4
Machine 3 7 4 4 2

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Accounting questions