Four trucks, 1, 2, 3, and 4, are waiting on a loading dock at XYZ Company that has only a single service bay. The trucks

Four trucks, 1, 2, 3, and 4, are waiting on a loading dock at XYZ Company that has only a single service bay. The trucks are labeled in the order that they arrived at the dock. Assume the current time is 1:00 p.m. The times required to unload each truck and the times that the goods they contain are due in the plant are given in the following table.


Truck

Unloading Time (minutes)

Time Material Is Due

1

20

1:25 p.m.

2

14

1:45 p.m.

3

35

1:50 p.m.

4

10

1:30 p.m.


Determine the schedules that result for each of the rules FCFS, SPT, EDD, and CR. In each case compute the mean flow time, average tardiness, and a number of tardy jobs.


Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Statistics Principles And Methods

Authors: Richard A. Johnson, Gouri K. Bhattacharyya

7th Edition

8126557745, 470904119, 978-0470904114

More Books

Students also viewed these Mathematics questions