From the following data, calculate (i) labour cost variance (ii) labour efficiency variance (iii) labour rate variance and others. Workmen Standard Actual for 620,000 tiles
From the following data, calculate (i) labour cost variance (ii) labour
efficiency variance (iii) labour rate variance and
others.
Workmen
Standard
Actual for 620,000 tiles
Hrs.
Rate
Total
Hrs.
Rate
Total
Workmen A
20
3
60
30
3
90
Workmen B
25
4
100
15
4.5
67.5
160
157.5