Question

1 Approved Answer

From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many

From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take?

image text in transcribed
ID Description Predecessor Time A Survey site None 6 B Excavate site A 5 Install power lines B 4 D Install drainage B W H m Pour foundation C, D The project will take days. The critical path is The late start on Activity C is days. The slack on Activity C is days. The slack on Activity D is days. The early start on Activity E is days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project management the managerial process

Authors: Eric W Larson, Clifford F. Gray

5th edition

73403342, 978-0073403342

More Books

Students also viewed these General Management questions

Question

Explain the cost of capital.

Answered: 1 week ago

Question

Define capital structure.

Answered: 1 week ago

Question

List out some inventory management techniques.

Answered: 1 week ago