Question
Garment Ltd. is a clothing manufacturer that uses a standard costing system and flexible budget for factory overhead. Standard cost details for producing one jacket
Garment Ltd. is a clothing manufacturer that uses a standard costing system and flexible budget for factory overhead. Standard cost details for producing one jacket is given below:
Direct Material (1.35 meters per unit @ $12.60 per meter) $ 17.01
Direct Labour (0.75 hrs per unit @ $22 per hour ) $ 16.50
Factory Overhead $ 15.00
Total Standard Cost per Unit $ 48.51
For the month of April, the following actual results were observed:
7,200 meters of direct material were purchased at a cost of $95,200
The company had beginning direct material of 450 meters and ending material of 800 meters for the period.
Direct labour usage was 4,100 Direct Labour Hours (DLH) at a cost of $20.00 per DLH.
Production: 5,150 jackets
Required: Calculate direct labour efficiency variance: [DLEV]
DLEV = (AH-SH) x SR
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started