Generic Company purchased land for P2,000,000 as a plant site. There was a small office building on the land with fair value of P700,000 which

Generic Company purchased land for P2,000,000 as a plant site. There was a small office building on the land with fair value of P700,000 which the entity will continue to use with some modification and renovation.

The entity decided to construct a factory building and incurred the following costs:

Materials and supplies

3,000,000

Excavation

100,000

Labor on construction

2,500,000

Cost of remodeling old office building

200,000

Imputed interest on corporations own money used during construction

120,000

Cash discounts on materials purchased

60,000

Supervision by management during construction

70,000

Compensation insurance premiums for workers

20,000

Payment of claim for injuries not covered by insurance

25,000

Clerical and other expenses during construction

30,000

Paving of streets and sidewalks

40,000

Plans and specifications

140,000

Legal cost of conveying land

10,000

Legal cost of injury claim

15,000

1. What is the cost of land?

2. What is the cost of office building?

3. What is the cost of factory building?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hospitality Financial Accounting

Authors: Jerry J. Weygandt, Donald E. Kieso, Paul D. Kimmel, Agnes L.

2nd Edition

9780470598092, 470083603, 978-0470083604

More Books

Students also viewed these Accounting questions