Geoff coolly surveyed his earned value table at the conclusion of month 24 . It was hard to believe that two short years ago, with

Geoff coolly surveyed hisearned valuetable at the conclusion ofmonth 24. It was hard to believe that two short years ago, with his membership at Match.com about to expire, he had managed to craft an ad that was both urbane and manly enough as to catch the eye of the divine Miss Smylie.(The male model photo he substituted for his own certainly didn't hurt either.)Now he was almost done managing this critical project. Some might think him crass for taking such an approach, but he practiced what he preached at the small school where he taught.

image text in transcribed
Activity 4 8 12 16 20 24 28 Total % Complete Courtship 1000 2000 3000 3000 3000 1000 13000 90% Proposal 500 5000 5000 10500 100% Negotiations 500 1000 1500 100% Invitations 800 800 100% Showers 400 800 800 2000 100% Musicians 400 1000 1400 20% Caterer 200 2000 5000 7200 30% Rehearsal 400 4000 4400 10% Party 1000 2000 3000 20% Ceremony 500 500 500 500 3500 5500 20% Reception 1000 1000 6000 8000 30% Honeymoon 2000 4000 6000 40% Total 1000 3000 10700 5900 9700 7500 25500 63300 Cumulative 1000 4000 14700 20600 30300 37800 63300 Actual 2500 5100 12700 6400 10600 9000 0 Cumulative 2500 7600 20300 26700 37300 46300 Actual

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hospitality An Introduction

Authors: Robert A Brymer, Misty M Johanson

14th Edition

0757588638, 9780757588631

More Books

Students also viewed these General Management questions

Question

2. How do I perform this role?

Answered: 1 week ago