Georgia Scott wants to use a Project view that identifies her project's critical path. Which option should she select to most directly identify the critical
Georgia Scott wants to use a Project view that identifies her project's critical path. Which option should she select to most directly identify the critical path? A The Calendar view B The Tracking Gantt view C The default Gantt Chart view D The Resource Usage view