Gerta is faced with a big rush on her project due to a demand from the customer to bring the end - date in by
Gerta is faced with a big rush on her project due to a demand from the customer to bring the enddate in by weeks. She decides to add new coders and testers to accelerate the timeline. Gerta has chosen which form of schedule compression?
a
Critical Path Merging
b
Crashing
c
FastTracking
d
Escalation