Question

00
1 Approved Answer

Given an activity's optimistic, most likely, and pessimistic time estimates of 4 , 1 4 , and 1 8 days respectively, compute the PERT expected

Given an activity's optimistic, most likely, and pessimistic time estimates of 4,14, and 18 days respectively, compute the PERT expected activity time for this activity.
a.
14
b.
12
c.
11
d.
13