Given the activity table ( Table of Dependencies ) below for a certain project: table [ [ Activity , Predecessor,Duration ( Weeks ) ]
Given the activity table Table of Dependencies below for a certain project:
tableActivityPredecessor,Duration WeeksABACADAEBFCGEHDFG
a Calculate the project duration using the forward pass calculate the critical path using the backward pass Marks
b Based on the answers obtained in question a and the Table of Dependencies; construct a Gantt chart. Marks