Question

1 Approved Answer

Given the following activity's optimistic, most likely, and pessimistic, time estimates of 6, 10, 14 days, respectively, the PERT variance for this activity is ____days?

Given the following activity's optimistic, most likely, and pessimistic, time estimates of 6, 10, 14 days, respectively, the PERT variance for this activity is ____days?

Please show the steps on how to find the variance given the information provided in the question.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Sustainability and Supply Chain Management

Authors: Jay Heizer, Barry Render, Paul Griffin

2nd Canadian edition

978-0133764345

More Books

Students also viewed these General Management questions