Given the following case study, can you help me come up with a detailed schedule of activities for the project? CASE STUDY HONICKER CORPORATION Honicker
Given the following case study, can you help me come up with a detailed schedule of activities for the project?
CASE STUDY
HONICKER CORPORATION
Honicker decided to acquiring four companies around the world: Alpha, Beta, Gamma, and Delta Companies.
Honicker decided to leave each company's senior management teams intact, provided that the necessary changes, as established by corporate, could be implemented.
Honicker wanted each company to have the manufacturing capability to supply parts to any Honicker client worldwide. Honicker had an enterprise project management methodology (EPM) that worked well. Honicker wanted to expand their EPM to the four aquired companies knowing they might want some changes to be made.
The four acquired divisions were all at different levels of project management maturity. Alpha did have an EPM system and believed that its approach to project management was superior to the one that Honicker was using.
Beta Company was just beginning to learn project management but did not have any formal EPM system, although it did have a few project management templates that were being used for status reporting to its customers.
Gamma and Delta Companies were clueless about project management.
Laws in each of the countries where the acquired companies were located created other stakeholders that had to be serviced, and all of these stakeholders were at different levels of project management maturity. In some countries, government stakeholders were actively involved because of employment procurement laws, whereas in other countries government stakeholders were passive participants unless health, safety, or environmental laws were broken.
Honicker also knew that there is never an acquisition of equals; there is always a "landlord" and "tenants," and Honicker is the landlord. But acting as a landlord and exerting influence in the process could alienate some of the acquired companies and do more harm than good. Honicker's approach was to treat this as a project, and each company, along with its clients and local stakeholders, would be treated as project stakeholders. Using stakeholder relations management practices would be essential to getting an agreement on the project management approach.
Honicker requested that each company assign three people to the project management implementation team that would be headed up by Honicker personnel. The ideal team member would have some knowledge and/or experience in project management and be authorized by their senior levels of management to make decisions for their company. The representatives should also understand the stakeholder needs from their clients and local stakeholders. Honicker wanted an understanding to be reached as early as possible that each company would agree to use the methodology that was finally decided upon by the team.
Senior management in each of the four companies sent a letter of understanding to Honicker promising to assign the most qualified personnel and agreeing to use the methodology that was agreed upon. Each stated that their company understood the importance of this project.
The first part of the project would be to come to an agreement on the methodology. The second part of the project would be to invite clients and stakeholders to see the methodology and provide feedback.
Honicker had hoped that the team could come to an agreement on a companywide EPM system within six months. But after the kickoff meeting was over, Honicker realized that it would probably be two years before an agreement would be reached on the EPM system. Several issues became apparent at the first meeting:
- Each company had different time requirements for the project.
- Each company saw the importance of the project differently.
- Each company had its own culture and wanted to be sure that the final design was a good fit with that culture.
- Each company saw the status and power of the project manager differently.
- Despite the letters of understanding, two of the companies, Gamma and Delta, did not understand their role and relationship with Honicker on this project.
- Alpha wanted to micromanage the project, believing that everyone should use its methodology
Senior management at Honicker asked the Honicker representatives at the kickoff meeting to prepare a confidential memo on their opinion of the first meeting with the team. The Honicker personnel prepared a memo including the following comments:
- Not all of the representatives at the meeting openly expressed their true feelings about the project.
- It was quite apparent that some of the companies would like to see the project fail.
- Some of the companies were afraid that the implementation of the new EPM system would result in a shift in power and authority.
- Some people were afraid that the new EPM system would show that fewer resources were needed in the functional organization, thus causing a downsizing of personnel and a reduction in bonuses that were currently based on headcount in functional groups.
- Some seemed apprehensive that the implementation of the new system would cause a change in the company's culture and working relationships with their clients.
- Some seemed afraid of learning a new system and being pressured into using it.
It was obvious that this would be no easy task. Honicker had to get to know all companies better and understand their needs and expectations. Honicker management had to show them that their opinion was of value and find ways to win their support.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started