Given the following cash flow for project A: C 0 = -3,000, C 1 = +500, C 2 = +1,500 and C 3 = +5,000,
Given the following cash flow for project A: C0 = -3,000, C1 = +500, C2 = +1,500 and C3 = +5,000, calculate the NPV of the project using a 15% discount rate.