Question
1 Approved Answer
Given the following cost and activity observations for Bounty Company's utilities, use the high-low method to determine Bounty's variable utilities cost per machine hour. Round
Given the following cost and activity observations for Bounty Company's utilities, use the high-low method to determine Bounty's variable utilities cost per machine hour. Round your answer to the nearest cent. Machine Hours Cost March $3,087 14,787 April 2,667 10,248 May 2,826 11,624 June 3,585 17,674 a. $0.74 Ob. $0.70 Oc. $1.48 Od. $0.12
Step by Step Solution
There are 3 Steps involved in it
Step: 1