Given the following Cost Baseline, what is the project Schedule Variance (SV) at the end of Period 2, if Activity A is 25% complete and
Given the following Cost Baseline, what is the project Schedule Variance (SV) at the end of Period 2, if Activity A is 25% complete and Activity B is 40% complete.
Group of answer choices
A $-10
B $10
C $-20
D $22