Given the following data for the tasks in a production process, which of the options shows the critical tasks? Task name Duration ( days )
Given the following data for the tasks in a production process, which of the options shows the critical tasks?
Task name
Duration days
Immediate Predecessor
A
B
A
C
A B
D
A
E
D
F
C E
A D E BC F
A B C F
A D E F
A D E C F