Given the following data / information, determine the elevation of the weir crest at the river (8 marks): Ground level at head of scheme =
Given the following data / information, determine the elevation of the weir crest at the river (8 marks):
- Ground level at head of scheme = 2000 m amsl;
- Operation head = 0.50 m
- Canal length to head works = 5.0 km
- Slope of the canal = 0.5%
- Head loss across structures = 1.50m
- Head loss at intake = 0.10m
Step by Step Solution
★★★★★
3.48 Rating (151 Votes )
There are 3 Steps involved in it
Step: 1
The detailed answer for the above question is provided below Head of scheme 20000 WL hea...