Question

1 Approved Answer

Given the following estimates for all activities of a project (in days) Activity Optimistic A B C D E F 4 2 2 3

image 

Given the following estimates for all activities of a project (in days) Activity Optimistic A B C D E F 4 2 2 3 5 2 Most Likely 7 5 5 8 7 Pessimistic 10 6 8 a 17 12 The Critical Path is A-B-E-F. What would the average have to be to ensure a 95 percent chance of completing the project in 30 days?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

To solve this we can leverage the concept of Critical Path Method CPM and apply a safety factor to t... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Processes And Supply Chains

Authors: Lee Krajewski, Naresh Malhotra, Larry Ritzman

13th Global Edition

129240986X, 978-1292409863

More Books

Students also viewed these General Management questions