Question
Given the following Gantt: Perform the analysis at the end of each day that is specified, Using the ACWP, BCWP and BCWS totals calculate the
Given the following Gantt: Perform the analysis at the end of each day that is specified, Using the ACWP, BCWP and BCWS totals calculate the CPI, CV, SPI, and SV for the project. Each cut in time is independent. $100/day penalty. Indirect costs $50/day.
a) At the end of day 4th, Activity B, 60% of the work done. Activity F, 80% of the work done.
b) At the end of day 8th, Activity C, 80% of the work done. Activity G, 90% of the work done
c) At the end of day 11th, Activity D, 25% of the work done, Activity H, 30% of the work done.
d) At the end of the 16th
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started