Question
Given the following information, draw the project network diagram compute the ,early , late and slake time for each activity. Identify the critical path (CP)
- Given the following information, draw the project network diagram compute the ,early , late and slake time for each activity. Identify the critical path (CP)
- Use PERT to analyze the chance the delays on CP activities does not push the project duration beyond 40 days.
ID | Optimistic | Most likely | Pessimistic | Predecessor |
A | 2 | 4 | 6 | None |
B | 10 | 11 | 12 | A |
C | 5 | 6 | 9 | A |
D | 2 | 8 | 8 | A |
E | 5 | 6 | 15 | B,C |
F | 2 | 2 | 2 | D |
G | 3 | 5 | 7 | E,F |
H | 7 | 7 | 17 | F |
I | 3 | 6 | 8 | G,H |
Step by Step Solution
3.29 Rating (155 Votes )
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Project management the managerial process
Authors: Eric W Larson, Clifford F. Gray
5th edition
73403342, 978-0073403342
Students also viewed these Computer Engineering questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App