Question: Given the following information, draw the project network diagram compute the ,early , late and slake time for each activity. Identify the critical path (CP)

  1. Given the following information, draw the project network diagram compute the ,early , late and slake time for each activity. Identify the critical path (CP) 
  2. Use PERT to analyze the chance the delays on CP activities does not push the project duration beyond 40 days. 
ID
Optimistic
Most likely
Pessimistic
Predecessor
A
2
4
6
None
B
10
11
12
A
C
5
6
9
A
D
2
8
8
A
E
5
6
15
B,C
F
2
2
2
D
G
3
5
7
E,F
H
7
7
17
F
I
3
6
8
G,H

Step by Step Solution

3.29 Rating (155 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Computer Engineering Questions!