Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC

Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV $22,000 EV $20,000 AC $25,000 BAC $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? c. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned? d. Use the SPI to estimate how long it will take to end project. e. Sketch the earned value chart for this project, using Figure 7-6 as a guide.

image text in transcribed
An EAC Estimate at completion (EAC) point above 120,000 and to the 100,000 Budget at completion (BAC) right of the BAC point means the 80,000 project is projected to Planned value (PV) cost more $ 60,000 and take 40 000 Actual cost (AC) longer than planned. Earned value (EV) 20 000 3 4 5 6 7 8 9 10 11 12 13 Month Actual cost (AC) - Planned value (PV) = = Earned value (EV)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management The Managerial Process

Authors: Eric W Larson, Clifford F. Gray

8th Edition

1260570436, 978-1260570434

More Books

Students also viewed these General Management questions