Given the following information for a project, determine the critical path. Activity Immediate Predecessor Activity Time ( days ) A - 6 B - 8
Given the following information for a project, determine the critical path.
Activity
Immediate Predecessor
Activity Time days
A
B
C
A B
D
B
E
C
F
C D
G
D
H
E F G
Question options:
ACEH
BCEH
BCFH
BDGH
BDFH