Given the following information: Powder factor/charge density is 0.9 kg/m3 5 x 5 m tunnel excavation Overbreak 10% Hole diameter of 127 mm Overall explosives
Given the following information: Powder factor/charge density is 0.9 kg/m3 5 x 5 m tunnel excavation Overbreak 10% Hole diameter of 127 mm Overall explosives cost average $5.0/kg Depth drilled per round 3.0 m Depth pulled per round 3.0 m 1. Calculate the Volume of rock blasted? 2. Calculate the cost of explosives