Given the following project network: a . Identify the critical path. A - C - D - F A - C - E - F
Given the following project network:
a Identify the critical path.
ACDF
ACEF
ABDF
b Identify the early start for task
c Identify the late finish for task C
d Calculate slack for task E
Step by Step Solution