Given the following project network and baseline information below, complete the form to develop a status report for the project at the end of period 4 and the end of period 8 . (Do not round intermediate calculations. Aound your table answer entries to the nearest whole number) \begin{tabular}{|c|c|c|c|c|c|c|} \hline End of Period 4 & \multicolumn{1}{|c|}{} & & & \\ \hline Task & Actual \% Complete & EV & AC & PV & CV & SV \\ \hline A & Finished & & 300 & & \\ \hline B & 60 & & 900 & & \\ \hline C & 25 & & 500 & & \\ \hline D & 0 & & & & \\ \hline E & 0 & & & & \\ \hline Cumulative Totals & & & & \\ \hline \end{tabular} \begin{tabular}{|c|c|r|r|r|r|r|} \hline End of Period 8 & & & & & & \\ \hline Task & Actual \% Complete & EV & AC & PV & CV & SV \\ \hline A & Finished & & 300 & & & \\ \hline B & Finished & & 2,000 & & & \\ \hline C & Finished & & 1,600 & & & \\ \hline D & 30 & & 400 & & & \\ \hline E & 25 & & 400 & & & \\ \hline F & 0 & & & & & \\ \hline \end{tabular} Given the following project network and baseline information below, complete the form to develop a status report for the project at the end of period 4 and the end of period 8 . (Do not round intermediate calculations. Aound your table answer entries to the nearest whole number) \begin{tabular}{|c|c|c|c|c|c|c|} \hline End of Period 4 & \multicolumn{1}{|c|}{} & & & \\ \hline Task & Actual \% Complete & EV & AC & PV & CV & SV \\ \hline A & Finished & & 300 & & \\ \hline B & 60 & & 900 & & \\ \hline C & 25 & & 500 & & \\ \hline D & 0 & & & & \\ \hline E & 0 & & & & \\ \hline Cumulative Totals & & & & \\ \hline \end{tabular} \begin{tabular}{|c|c|r|r|r|r|r|} \hline End of Period 8 & & & & & & \\ \hline Task & Actual \% Complete & EV & AC & PV & CV & SV \\ \hline A & Finished & & 300 & & & \\ \hline B & Finished & & 2,000 & & & \\ \hline C & Finished & & 1,600 & & & \\ \hline D & 30 & & 400 & & & \\ \hline E & 25 & & 400 & & & \\ \hline F & 0 & & & & & \\ \hline \end{tabular}