Given the following project status information:EV=$6,800, PV=$7,150,and AC=$6,950, what is the current schedule performance index (SPI) for this project this can be expressed in decimal
Given the following project status information:EV=$6,800, PV=$7,150,and AC=$6,950, what is the current schedule performance index (SPI) for this project this can be expressed in decimal or percentage format