Given the following queue of 3 jobs to be processed at Enya's workstation: # Days Until Due 12 20 13 Job A B C O
Given the following queue of 3 jobs to be processed at Enya's workstation: # Days Until Due 12 20 13 Job A B C O 1.33 What is the average tardiness if the DDATE sequence is used? O 1.67 O 2.00 O 2.33 Processing Time (Days) O 2.67 5 13 9