Question
Given the following task time estimates (HOURS), Task Time Predecessor A 40 B 20 C 25 A D 19 A, B E 25 C, D
Given the following task time estimates (HOURS),
Task | Time | Predecessor |
A | 40 | |
B | 20 | |
C | 25 | A |
D | 19 | A, B |
E | 25 | C, D |
F | 24 | E |
G | 18 | F |
a. How long is the project length? [ Select ] ["134.83", "122.00", "127.45", "135.78", "132.00"] .
b. What tasks form the critical path? [ Select ] ["B, C, D, E, F, G", "A, B, C, E, F, G", "B, D, E, F, G", "A, D, E, F, G", "A, C, E, F, G"]
c. What is the LS/LF for activity D.? [ Select ] ["65 and 90", "44 and 55", "34.56 and 4.78", "50.19 and 7.08", "46 and 65"] .
d. How much slack is there in activity C? [ Select ] ["8.34 hours", "29 hours", "6 hours", "0", "12 hours"] How much slack in activity D? [ Select ] ["5 hours", "26 hours", "0, it is on the critical path", "28 hours", "6 hours"]
e. What if activity D. was delayed by 6 hours, what would be the project length and critical path? [ Select ] ["133 hours; A, C, E, F, G", "132 hours; B, C, D, E, F, G", "132 hours; A, C, D, E, F, G", "130 hours; B, C, E, F, F", "no change in either the critical path or project length"]
f. Referring to letter e., how much slack would be in activity B.? [ Select ] ["8 hours", "26 hours", "0 (zero), it is now on the critical path", "6 hours", "20 hours"]
Please provide in depth explanation as dumb down as possible. Thank you.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started