Given the improvement curve data calculate the cost objective for unit #8 labor hours for unit #4 120 hours labor hours for unit #1 160
Given the improvement curve data calculate the cost objective for unit #8
labor hours for unit #4 120 hours
labor hours for unit #1 160 hrs
rate of improvement 10%
improvement curve slope 90%
Step by Step Solution