Given the information below, how long is the Critical Path? Activity Time Immediate Predecessor A 2 ---- B 4 ---- C 5 A D 4
Given the information below, how long is the Critical Path? Activity Time Immediate Predecessor A 2 ---- B 4 ---- C 5 A D 4 B E 7 C, D F 2 E G 9 F H 6 F I 7 G, H J 10 D