Question
Given the network and cost information below, develop a Financial Requirements Schedule and Budget. Make a table of your budget, assuming costs are distributed linearly.
Given the network and cost information below, develop a Financial Requirements Schedule and Budget. Make a table of your budget, assuming costs are distributed linearly.
Activity | Duration | ES | LS | EF | LF | Slack | Budget |
1-2 | 5 | 0 | 7 | 5 | 12 | 7 | 25 |
1-3 | 8 | 0 | 0 | 8 | 8 | 0 | 48 |
1-4 | 6 | 0 | 5 | 6 | 11 | 5 | 30 |
2-5 | 3 | 5 | 12 | 8 | 15 | 7 | 9 |
3-4 | 3 | 8 | 8 | 11 | 11 | 0 | 12 |
4-5 | 4 | 11 | 11 | 15 | 15 | 0 | 20 |
Assume the following information has been collected for you. Complete the Current Project Status Report given on the next page ( i.e. page 3 ). From your completed report, develop a revised budget requirements table. What information would you offer at the next Project Management/Review Meeting.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started