Given the portion of the network shown above, what is the latest start time of activity D if the latest finish of activity F is
Given the portion of the network shown above, what is the latest start time of activity D if the latest finish of activity F is 26 and the latest finish of activity G is 34 ? A) 9 B) 6 C) none of these D) 5