Given the project within the table below, calculate the following: Activity Predecessor Time ( days ) A - - 7 . 5 B - -

Given the project within the table below, calculate the following:
Activity Predecessor Time (days)
A --7.5
B --9.7
C --10.5
D A, C 8.8
E D 10
F B, E 4.2
G F 9.7
H G 11.5
a. What is the project length?
[ Select ]
b. What activities are on the critical path?
[ Select ]
c. How much slack is in activity A?
[ Select ]
, and activity B?
[ Select ]
d. What is the Late Start / Late Finish for activity B?
[ Select ]
e. What would happen to the overall project length if activity E was delayed by 4 days, now taking a total of 14 days?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Quantitative Analysis For Management

Authors: Barry Render, Ralph M. Stair, Michael E. Hanna

11th Edition

9780132997621, 132149117, 132997622, 978-0132149112

More Books

Students also viewed these General Management questions