Given the project within the table below, calculate the following: ( a ) The critical path B - D - E - F - G

Given the project within the table below, calculate the following:
(a) The critical path
B-D-E-F-G
(b) The project duration 23
(c) The amount of slack for activity
\table[[Activity,\table[[Duration],[(hours)]],\table[[Immediate],[Predecessors]]],[A,14,None],[B,10,None],[C,3,None],[D,7,B,C],[E,1,D],[F,1,E],[G,4,A,F]]
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management in the Supply Chain Decisions and Cases

Authors: Roger Schroeder, M. Johnny Rungtusanatham, Susan Goldstein

6th edition

73525243, 978-0073525242

More Books

Students also viewed these General Management questions

Question

how to calculate the total number of payment periods per loan

Answered: 1 week ago