Given the unit data in Table , calculate the production cost for a 250-MW demand. Unit Capacity(MW) Forced Outage Rate $/MWh A 100 0.1 15
Given the unit data in Table , calculate the production cost for a 250-MW demand.
Unit | Capacity(MW) | Forced Outage Rate | $/MWh |
A | 100 | 0.1 | 15 |
B | 150 | 0.2 | 25 |
C | 200 | 0.25 | 40 |
TIE | 1000 | 0 | 80 |
(1) Give the deterministic solution (no outages).
(2) Give the deterministic solution with unit derating.
(3) Give the probabilistic solution using state enumeration.
(4) Give the probabilistic solution using the convolution method
Step by Step Solution
★★★★★
3.44 Rating (147 Votes )
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started