Given the WBS , what is the latest start for activity C ? Activity ( WBS ) Immediate Activity Time Predecessors ( weeks ) Start
Given the WBS what is the latest start for activity C
Activity WBS Immediate Activity Time
Predecessors weeks
Start None
AKickoff Meeting Start
BSelect administrative staff A
CSelect system configuration B
DSelect Sonar option B
ECreate technical data package BCD
F Evaluate parts options C
G Decide on parts D
H Inform client of parts selection EFG
I. Order parts FH